Page History: Project Control - Shipping Events
Compare Page Revisions
Page Revision: Mon, 03 Dec 2012 13:34
Default Menu Location
Maintain ==> Project Control==> Projects ==> Shipping Events
General Description
This tab displays all the shipping events associated with a project.
Fields/Filters
SE#: The number of the selected shipping event. Adjutant automatically assigns shipping numbers with the project number, a hyphen and a sequential letter (for example, "757-A"). The SE# also appears under the "SE#" column in the grid of Shipping Events, and the sequential letter appears under "Suffix".
Name: Shipping Event name.
ShipTo: The person or organization receiving the shipment. When you choose the Recipient from the drop-down menu, its address appears below.
Ship Date: Estimated date the Event will ship. Also appears under "Est. Date" in the grid of Shipping Events.
Cutoff Date: OnSite Date: The date which the contents must be on site (delivered and on site) by.
ShipVia: The method of shipping.
Carrier: Truck Type:Ship Whse: Warehouse that this will be shipping out of.
Estimated Value: Estimated value of the contents being shipped.
Estimated Weight: Estimated weight of the contents being shipped.