Auto-Schedule
Modified on Wed, 18 Mar 2009 11:13 by tsanchez — Categorized as: Task Management
Table of Contents
[
Hide/Show
]
General Information
General Use
Assigning Hours
General Information
¶
The
Auto-Schedule screen
is accessed from the
Assignments section of the Task Entry screen
via the Auto-Schedule icon.
Auto-Schedule Icon
It displays all assignable resources, along with their availability on a day-by-day basis.
General Use
¶
To correctly use the Auto-Schedule screen, you must first select a Skill Set and enter a Total Duration, Start Date and Time on the Assignments tab.
Click here for an illustration
.
By default, the Auto-Schedule screen will display:
All resources with the Skill Set you selected on the Assignment
Fourteen days of the schedule, starting with the date you entered on the Assignment
Each resource's availability on a day-by-day basis:
Days with available hours are highlighted in green.
Days without available hours are not highlighted.
Non-working days are highlighted in red.
You can filter the resources by Squad by using the
Squad drop-down menu
.
You can view additional weeks by using the Forward Arrow button.
You can refresh the screen by clicking the Refresh button.
Assigning Hours
¶
There are two ways to assign hours:
1. All hours to the same resource 2. Hours to different resources/days
To assign all hours to the same resource, double-click the resource's name. The program will assign the hours so that the task will be completed as soon as possible.
To assign hours to different resources/days, you can double click an individual date field in the grid.
Once you have assigned all of the hours, click the Assign button on the bottom-right hand side of the screen.